homeinfrastructure NewsBig boost for home buyers: Projects received part occupation certificate to come under MahaRERA

Big boost for home buyers: Projects received part occupation certificate to come under MahaRERA

In an order that would set a precedent for future cases related to part occupation certificate, the MahaRERA (Maharashtra Real Estate Regulatory Authority) in an interim order dated September 12 has held that the project will come under its jurisdiction even though it has received part occupation certificate.

By Ashwini Priolker  Oct 5, 2018 12:58:01 PM IST (Updated)


In an order that would set a precedent for future cases related to part occupation certificate, the MahaRERA (Maharashtra Real Estate Regulatory Authority) in an interim order dated September 12 has held that the project will come under its jurisdiction even though it has received part occupation certificate.
In its order, MahaRERA implied that having part occupation certificate means the project is not completed. The ruling is very significant as getting part occupation certificate for the projects is quite a trend among the developers in Maharashtra.
“This will be a welcome order for the home buyers. The projects with part occupation certificate will now be considered as ongoing projects. This means, they will now come under the purview of RERA,” said Apurva Kanvinde, senior associate, Juris Corp.