Mumbai-Ahmedabad Bullet Train work picking up speed: A look at its status

The bullet train will be run between Ahmedabad and Mumbai crossing 12 stations on the way on a high-speed rail corridor.

By CNBCTV18.com Nov 19, 2022 1:18:11 PM IST (Published)

3 Min Read

The Mumbai-Ahmedabad Bullet Train project is picking up speed. The 508.17-kilometre-long network will pass through 12 stations between Mumbai and Ahmedabad. The last status report was shared in August by the National High-Speed Rail Corporation Ltd which is executing the project, and recently a new tender has been floated for the completion of the last leg of the project.

The Latest Update
The NHSRC has floated tenders for the final 135km stretch of the Mumbai-Ahmedabad bullet train project. This includes viaduct, mountain tunnels and three stations and with this, bids for the entire 508km corridor will be up for submission.
The 135km stretch outside Mumbai falls between Shilphata and Zaroli on the Maharashtra-Gujarat border. There are three stations to be built in that stretch, which are Thane, Virar and Boisar.